+ April 1st, 2023 - Some packages not picked up by UPS and USPS; those packages have been dropped off.
+ March 29th, 2023 - All GB Orders shipped. If you did not received a tracking email, please check your spam; if not there, reply to your original order confirmation email and I will send you the tracking.
+ March 26th, 2023 - 75% of orders shipped.
+ March 23rd, 2023 - 50% of orders shipped.
+ March 21st, 2023 - GB Orders are shipping. About 25% shipped.
+ March 2nd, 2023 - E-White Orders have been shipped. Cerakoted boards will be finished by end of week and shipped out ASAP
+ January 26th, 2023 - While repacking cases after Cerakote, an issue was caught that affected a lot of cases. All the affected cases are being re-coated. New estimated ship date will be given as soon as possible.
+ December 30th, 2022 - PCBs have arrived, tested, and are pre-flashed with Vial firmware
+ December 22nd, 2022 - Cases are being Cerakoted. PCBs are in shipment to HQ
+ December 9th, 2022 - Cases are being Cerakoted, PCBs nearing completion with manufacturer. New estimated ship date is Early to Mid January
+ October 21st, 2022 - Cases dropped off for Cerakote
+ October 19th, 2022 - Cases arrived at Fruitykeeb. QC underway.
+ October 10th, 2022 - Cases shipped from manufacturer
+ September 29th, 2022 - Cases finished, will ship after National Day
+ June 18th, 2022 - Order placed with manufacturer
+ May 31st, 2022 - GB Closed. All units sold out.